The George

Project Status

Q1 2019: All structures have now been removed from site. A temporary trail is being constructed along the south property line of the site to provide an alternate route for pedestrians.

Council have previously approved a Land Exchange Agreement and have completed the Road Closure Bylaw necessary to close Winn Road. A new road dedication will be created that is the same land area as Winn Road but shifted and realigned to match the planned Plaza area. A significant amount of work, including extensive peer review by hydrogeologists and geotechnical engineers working for the Town, was conducted to arrive at the current approved methodology for ground improvement and excavation. The safety of the aquifer continues to the be the key focus for staff and other professionals working on this project. The planned excavation will not be encroaching into the glacial till layer that protects the aquifer.

Staff are working with the developer to execute the terms of the Land Exchange Agreement which encompasses lot consolidation, road closure, and creation of an ‘airspace’ parcel. This airspace parcel will allow the parking lot to extend under the planned Town-owned Plaza.

Next steps will be for the developer to commence remediation of the site as well as ‘deep soil mixing’. This deep soil mixing mixes a cementitious grout with the existing soils to improve the bearing capacity of the soil. The deep soil mixing methodology was also reviewed on behalf of the Town by a leading expert in the field. (see video below for more details)

The building permit is being processed by staff but will not be issued until all terms of the Land Exchange agreement have been executed and civil design for off-site improvements have been finalized with staff.

Council approvals for this project have been completed. Moving forward, all remaining permits, processing and inspections will be conducted on a staff level. As the project progresses, staff will provide updates to Council and the public.

Aquifer Protection and the George

The Town has followed an extensive and exhaustive review process to ensure that the Gibsons Aquifer will be protected once the George Project gets underway. This video summarizes the results of this review and explains how the site clean-up and subsequent construction process will take place so that our Aquifer remains safe at every stage of site development. We have also provided responses to a number of Frequently Asked Questions about Aquifer Protection.

George Hotel and Residences Development Application

The George Hotel project received approval of the requested Official Community Plan amendment and Zoning Bylaw amendment on October 6, 2015. Since then, the project has worked on further details and review, in preparation for start of construction. All necessary Town Development Permits have now been issued and the project is ready to start construction. This web page will continue to provide regular updates on the status of this significant project.

Building Permit ready The Building Permit is ready to be issued once the developer decides to proceed

The Town Development Permits (see further down this page) and Building Permit allow for the following next steps:

  1. Demolition of remaining structures
  2. Remediation of Site Contamination
  3. Ground improvement in preparation of construction
  4. Start of construction
Development Permits issued
Development Permit for Form and Character (DPA5)Issued June 1, 2016
Environmentally Sensitive Areas Development Permit (DPA2)Issued August 1, 2017
Geotechnical Hazards Development Permit (DPA1)

Issued August 8, 2017

Aquifer Protection Development Permit (DPA9)

Issued August 1, 2017

Project description, drawings:

The project includes the following:

  • 39 residential units
  • 116 hotel rooms
  • Conference centre, including spa, pools, lounge / café (level 1)
  • Waterfront restaurant on a proposed pier in the Gibsons Harbour
  • underground parking stalls
  • New waterfront public walkway, along the shoreline as well as public access to part of the proposed pier
  • Inclusion of a portion of Winn Road as part of the development site and providing a public plaza that will retain public access to the waterfront

The following link provides a copy of the approved design of the buildings:

The Town and the applicant have entered into a Development Agreement, that outlines conditions and commitments that have been agreed to for the process of detailed design and for construction.

For detailed information about this proposed development, please review the documents in the Reports and Related Documents section below.

Reports and Related Documents
Timeline review process Links to Reports and Documents from the Review Process
July 31, 2017
July 11, 2017
June 20, 2017
June 20, 2017
April 18, 2017
July 19, 2016
May 17, 2016
Oct. 14, 2015
Oct. 6, 2015
Oct. 1, 2015
Sept. 24, 2015

Sept. 15, 2015
July 28, 2015
July 21, 2015
June 16, 2015
May 12, 2015
September 30, 2014
July 15, 2014
June 3, 2014
March 25,   2014

Appendix A to staff report – Design Package for Rezoning, Marked up with Changes in response to Advisory Planning Commission Recommendations, dated 2013-12-20

  • Part 1 General
  • Part 2 Floor Plans etc.
  • Part 3 Elevations etc.
  • Part 4 Views and Shadowing
  • Appendix B to staff report – Landscape Design and Drawings, PMB Landscape Architects, dated 2013-09-24 and 2013-10-09
January 14,   2014
November 15, 2013
  • Minutes Advisory Planning Commission meeting with recommendations
November 12, 2013
July 23, 2013
 Contact Information 
Town of Gibsons
Director   of Planning
Lesley-Anne Staats
tel: 604-886-2274
email: lstaats@gibsons.ca
Town website: www.gibsons.ca
Facebook: https://www.facebook.com/TownofGibsons
Applicant Klaus Fuerniss Enterprises Inc.
c/o Art Phillips, Planning Consultant
email: a.phil@eastlink.caProject website:
www.georgegibsonshotel.com