Skyline Drive - Town of Gibsons

Skyline Drive – Watermain Replacement & Road Repaving

The Town of Gibsons is moving ahead with important infrastructure upgrades on Skyline Drive to improve water service reliability and road conditions.

Project Overview

What’s Happening:

Replacement of the water main and full road repaving.

Where:

Skyline Drive – from Headlands Road to the top of the hill where it tees (see map/picture below).

If the budget allows, upgrades may also extend to:

  • Avalon Drive
  • Allion Way
  • Shoal Lookout

Why:

The existing water main and road surface are in poor condition. This upgrade will:

  • Improve water service reliability
  • Increase fire flow capacity
  • Enhance overall road safety and drivability

Timeline:

  • RFP Posted: April 14, 2025
  • Contract Award: Scheduled for May 20, 2025 (Council decision)
  • Construction Start Date: To be confirmed once contract is awarded

Who to Contact:

For more information or questions, please email:
infrastructure@gibsons.ca